Anchor
job_cost_setting_up_cost_codes_h_715
job_cost_setting_up_cost_codes_h_715
Cost codes are used to define and categorize the costs of a job. Cost codes serve as the building blocks of job costing and allow you to define the source of posting accounts and the revenue recognition method used.
Cost  Cost recognition in Job Cost consists of the cost code format or structure, cost code segments, cost codes, and cost code elements. In addition, you need to specify profit types (for Cost Plus contract and Cost Plus NTE contract jobs) and production measures that you can assign to cost codes.

Setting up cost codes involves the following, in the order displayed:
Setting up cost element names
Renaming cost code segments
Setting up the cost code format
Defining production measures
Saving predefined profit types
Setting up master cost codes

Table of Contents


Anchor
job_cost_dividing_a_job_into_seg_8166
job_cost_dividing_a_job_into_seg_8166
Dividing a job into segments

Large projects, activities, and organizations are often divided into smaller parts to facilitate their management. The following diagram shows how a job can be broken into cost elements and cost code segments (phases, steps, details, and components). Image Removed

Image Added


Anchor
job_cost_setting_up_cost_element_5841
job_cost_setting_up_cost_element_5841
Anchor
job_cost_setting_up_cost_element_3012
job_cost_setting_up_cost_element_3012
Anchor
job_cost_setting_up_cost_element_6521
job_cost_setting_up_cost_element_6521
Setting up cost element names

Cost elements are categories of costs on a typical job and are used to group similar costs or cost codes. Labor, Material, Equipment, Subcontractor, and Other serve as default cost elements. Four user-defined cost elements are also available.

You can accept the default cost element names or rename them. You cannot rename the Labor cost element because it is the only cost element used with payroll transactions. You should establish your cost elements before renaming your cost code segments.

Below is a list of the default cost elements

Cost elementDescription

1 - Labor

You can post transactions that include the Labor cost element to Job Cost payroll or Microsoft Dynamics GP Payroll. You can also post labor costs with job transaction entries.

2 - Material

If you're using Inventory Control, you can post transactions that include the Material cost element to Job Cost and Inventory Control. You can also post material costs with job transaction entries or accounts payable transactions.

3 - Equipment

If you're using Payables Management, you can enter equipment costs on a voucher and post to the payables record for the vendor from which you rented the equipment. You can also post equipment costs with job transaction entries or inventory transactions.

4 - Subcontractor

If you're using Payables Management, you can post Transactions that include the Subcontractor cost element to Payables Management. You can also post subcontractor costs with job transaction entries or inventory transactions.

5 - Other

This cost element is used to track miscellaneous costs that do not fall into one of the four default cost elements. Examples are manually calculated overhead amounts and freight. You can also post Other cost elements with job transaction entries, accounts payable, or inventory transactions.

Anchorjob_cost_setting_up_cost_element_193job_cost_setting_up_cost_element_1936 to 9 - Anchorjob_cost_setting_up_cost_element_8045job_cost_setting_up_cost_element_8045 User-defined

You can create up to four user-defined cost elements and define revenue and expense posting accounts. You can also post user-defined costs with job transaction entries, accounts payable, or inventory transactions.

  1. Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Cost Elements.
  2. You can change the names of the default and user-defined cost element descriptions.

...

6 to 9 -User-defined

You can create up to four user-defined cost elements and define revenue and expense posting accounts. You can also post user-defined costs with job transaction entries, accounts payable, or inventory transactions.

  1. Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Cost Elements.
  2. You can change the names of the default and user-defined cost element descriptions. 

    Note

    If you plan to modify any Job Cost reports using Report Writer, you must use the default name in the Internal Name column.


  3. To print the Cost Element Setup List report, choose File > Print or choose the printer button.
  4. Choose Save.

...

A segment represents a unique category of information, such as a business location, department, or account type. Default names for cost code segments are provided in the Cost Codes Segment Setup window. You can either save the default names or rename the segments to suit your needs. Note:

Note

If you rename a cost code segment, you must do

...

so before

...

 setting up your cost code format.

  1. Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Cost Code Segments.
  2. You can enter a new name for each cost code segment. For example, if you create cost codes and use the second segment to differentiate the cost codes by warehouse location, enter "location" instead of "phase."
  3. Choose Save.
  4. To print the Cost Code Segments List report, reopen the Cost Code Segment Setup window, and choose File > Print or choose the printer button.

...

The cost code format can contain one to four segments. Each segment can contain up to five alphanumeric characters. Each segment of a cost code represents a unique phase, step, detail, or component level of a job.

Note

...

If you rename a segment, you must do

...

so before

...

 setting up your cost code format.

  1. Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Cost Code Format.
  2. In the Number of Segments field, enter the number of segments for your cost codes. This is determined by how you plan to break down your jobs. You can enter up to four segments and can enter a maximum of five alphanumeric characters for each segment. Do not leave blank characters in segments. 

    Note

...

  1. You must enter at least one segment consisting of at least one character. You can use additional steps, details, and components. We do not recommend or support changing the format after you post costs.


  2. Choose Save.
Note

...

If you need to use large segment lengths in your company, you may need to change your Microsoft Dynamics GP user preferences to allow scrolling arrows in your cost code fields. To change preferences, choose Microsoft Dynamics GP > Tools > Setup > User Preferences. In the User Preferences window, mark the Horizontal Scroll Arrows check box

...

.

...

If you want to change the cost code format after saving, you must contact Key2Act Support. We do not recommend or support changing the cost code format after costs post in Job Cost.

Defining production measures

Production measures are used to track the number of units estimated or produced for a selected cost code. Typical measures are Hours and Each.

Note

...

You must set up production measures before you add cost codes to your jobs. This is necessary for assigning production and estimate measures to the cost codes. You can set up additional production measures in the Job Cost Codes Setup window.

A quantity-per-unit is calculated automatically for each cost code in the Job Cost Code Setup window. You can also compare actual production quantities for cost codes to estimated production quantities to help identify problems with a job.

...

  1. Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Profit Types.
  2. Choose Save. 

    Note

...

  1. You must open and save the Profit Type Setup window, even though you cannot change the defaults.


  2. To print the Profit Type Setup List report, reopen the Profit Type Setup window, and choose File > Print or choose the printer button.

Anchor
job_cost_saving_predefined_profi_3764
job_cost_saving_predefined_profi_3764
Description of profit types

  • 1 - Non-billable: Billing amount = 0.00
    Use this profit type when the cost amounts posted to the cost code for the job should not be billed to the customer, or if you want to track costs but not bill for costs.
  • 2 - None: Billing amount = cost amount
    Use this profit type when the cost amount charged to the cost code for the job will become the billable amount. This is the default profit type for all cost codes on Fixed Amount contract jobs.
  • 3 - Percent margin: Billing amount = cost / (1 - percent margin)
    Use this profit type when the billing amount is based on a desired profit margin for the cost code. This margin is assigned as the profit amount for the cost code. For example, if a unit's actual cost is $100, and you choose a percent margin of 24 percent, the billing amount is $131.58. (The calculation is: 100 / (1 - 0.24) = 131.58).
  • 4 - Percent of cost: Billing amount = cost + (cost x percent of cost)
    Use this profit type when the markup amount is calculated as a percentage of the actual cost for the cost code assigned to the job. This markup percent is assigned as the profit amount to the cost code. For example, if the actual cost for the cost code is $100, and you choose a percent of cost of 10 percent, the billing amount is $110.
  • 5 - Per unit amount: Billing amount = cost + (number of units x profit per unit)
    Use this profit type when the profit amount is calculated as a dollar amount per unit for the cost code. For example, if the cost of each unit is $10, and 10 units are used with a profit amount of $5 per unit, the billing amount is $150. (Cost is 10 x $10 = $100 and billing amount is $100 + ($10 x $5) = $150.)
  • 6 - Total dollar amount: Billing amount = cost + profit amountUse amount
    Use this profit type when the profit amount for the cost code equals a total dollar amount, regardless of the cost or number of units used. For example, enter a profit amount of $100 for the cost code. The amount billed for the cost code is cost plus $100.
  • 7 - Flat rate per cost code: Use this profit type when the billing amount for the cost code equals a total dollar amount, regardless of the cost or number of units used. The total amount billed for the cost code is entered as the profit amount for the cost code. For example, enter $10 as the total amount billed for the cost code. If your cost is $7, your profit is $3. If your cost is $8.50, your profit is $1.50.
  • 8 - Flat rate per unit: Use this profit type when the cost code is billed as a flat amount per unit regardless of the cost of the unit. The amount billed per unit for the cost code is entered as the profit amount for the cost code. For example, if you enter a billable amount of $25 for a labor cost code, you bill $25 per unit. If your cost per unit is $10, your profit per unit is $15. If your cost per unit is $22.50, your profit per unit is $2.50.
  • 9 - Service labor rate group: If you are also using Service Management, use this profit type to bill job customers for labor-only cost codes and establish billing amounts for labor transactions. Labor rates can be set up to reflect different rates for different pay codes. You can create labor rates by position or by department. This profit type is unavailable if you do not have the Service Management Labor Rates module. Contact Key2Act Sales if you would like to purchase this module.

...

Since the jobs a company performs are usually similar, many of the details of the job structure (including some cost codes) will be common to many jobs. Master cost codes are commonly used codes that can be easily assigned to jobs without reentering information.

When designing cost codes, keep in mind that the system sorts characters from left to right, with numbers taking priority over letters.

  1. Choose Anchorjob_cost_setting_up_master_cost__3347job_cost_setting_up_master_cost__3347Choose Microsoft Dynamics GP > Tools > Setup > Job Cost > Cost Code Setup > Master Cost Codes.
  2. Complete the following fields, as necessary.
    • Cost Element Type: The default is 1 for Labor.
    • Cost Code, Description: Enter a new cost code and description.
    • Profit Type ID, Profit Amount: Enter the profit type ID and profit amount. If you only use the cost code on Cost Plus contract jobs, assign a profit type ID. The profit type for all cost codes assigned to Fixed Amount contract jobs automatically defaults to None and cannot be changed. If all jobs have the same profit amount for this cost code, you can set a percentage or currency profit amount.
    • Service Labor Rate Group: Enter a service labor rate group. This field is enabled only if the profit type is 9 - Service Labor Rate Group. See Creating labor rate groups (optional).
    • Estimate Units, Estimate Amount/Unit, Estimate Amount, Estimate Measure, Estimate Measure Name: Enter estimate information. Generally, the estimate unit and estimate amount/unit are assigned at the job level. The Estimate Amount field fills in automatically. When you enter an estimate measure, the Estimate Measure Name field will complete.
    • Production Est. Qty, Production Qty/Unit, Production Measure, Production Measure Name: Enter production information. If all your jobs use the same production measures for this cost code, enter the production quantity needed to complete a typical job. The production quantity per unit is calculated automatically based on the Estimate Units field. Enter a production measure. The Production Measure Name field will complete.
    • Transaction Type: Enter the transaction type. Accept All as the default or choose from the drop-down list. Choices include ALL, Inventory Item, Vendor ID, and Purchase Order. If you choose Inventory Item, an Item Number field appears, allowing you to enter an inventory item. If you choose Vendor ID, you can enter a vendor as a subcontractor. See Adding subcontractors to a job record. If you choose Purchase Order, a PO Number field appears. Enter a purchase order number.
    • Workers Comp: Use the lookup button to choose a workers' compensation code.
    • Account Number: If you selected the Cost Code option in posting options setup, choose a general ledger posting account to post transaction costs assigned to this cost code. When you assign a general ledger account to a cost code in the Master Cost Code Setup window, the designation remains in effect when you add the cost code to a job in the Job Cost Codes Setup window. If you selected the Division posting option, you will not be able to choose an account in the Master Cost Codes Setup window. Instead, when you use the Job Cost Code window, a default account will appear, taken from your division account setup.
  3. Choose Save.
  4. To print the Cost Code Master Setup report, choose File > Print or choose the printer button.

...