You can view lien waivers, mark lien waivers as received, and reprint lien waivers using the Manage Lien Waivers window.
Table of Contents |
---|
Receiving lien waivers
- Choose Cards > Job Cost > Master Subcontractor.
- Choose a subcontractor and choose Manage Lien Waivers.
- Complete the following fields:
- Job Number: Choose a job.
- Vendor ID: This field defaults to the vendor selected in the Master Subcontractors Maintenance window or Subcontractors Maintenance window.
- Display: Choose the Unreceived radio button.
- Date Received: Mark this check box for the lien waiver(s) you want to receive, or choose Mark All.
- Choose Process. To unreceive lien waivers, unmark the Date Received check box and choose Process. To unreceive all lien waivers, choose Unmark All before Process.
Viewing received lien waivers
- Choose Cards > Job Cost > Master Subcontractor.
- Choose a Subcontractor and choose Manage Lien Waivers.
- Choose a job in the Job Number field. The Vendor ID defaults to the vendor selected in the Master Subcontractors Maintenance window or Subcontractors Maintenance window.
- Choose the Received radio button.
- To view the details of a check, mark the Date Received check box, then zoom on the Check Number field.
Reprinting lien waivers
- Choose Cards > Job Cost > Master Subcontractor.
- Choose a Subcontractor and choose Manage Lien Waivers.
- Choose a job in the Job Number field. The Vendor ID defaults to the vendor selected in the Master Subcontractors Maintenance window or Subcontractors Maintenance window.
- In the scrolling window, mark the check box next to the check(s) you want to reprint.
- Choose Reprint. The Print Lien Waivers window opens. The starting and ending check numbers default.
- Choose Process. The Printed field in the Manage Lien Waivers window updates with the current date for the lien waivers just printed.