Reports that are sorted per project number include Profit and Loss, Job Schedule, Over (Under) Billing, Backlog, Billing, Retention, Employee Summary, Costs by Period, and Labor Summary reports.

Table of Contents

Anchor
reports_dexterity_job_cost_proje_8639
reports_dexterity_job_cost_proje_8639
Profit and loss by project report

The

Anchor
reports_dexterity_job_cost_proje_5408
reports_dexterity_job_cost_proje_5408
 Profit and Loss by Project report lists customers, percent complete, contract earned, actual cost to date, and profit or loss for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Profit and Loss.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_7489
reports_dexterity_job_cost_proje_7489
Job schedule by project report

The

Anchor
reports_dexterity_job_cost_proje_7483
reports_dexterity_job_cost_proje_7483
 Job Schedule by Project report lists the contract, forecasted cost, anticipated profit, and contract-to-date amounts for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Job Schedule.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_3473
reports_dexterity_job_cost_proje_3473
Over (under) billing by project report

The

Anchor
reports_dexterity_job_cost_proje_5936
reports_dexterity_job_cost_proje_5936
 Over (Under) Billing by Project report lists posted costs, estimated profit, revenues earned, and billed to date amounts for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Over (Under) Billing.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_408
reports_dexterity_job_cost_proje_408
Backlog by project report

The

Anchor
reports_dexterity_job_cost_proje_6741
reports_dexterity_job_cost_proje_6741
 Backlog by Project report lists original contract, contract earned, and backlog amounts for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Backlog.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_9125
reports_dexterity_job_cost_proje_9125
Billing by project report

The

Anchor
reports_dexterity_job_cost_proje_4185
reports_dexterity_job_cost_proje_4185
 Billing by Project report lists total contract, gross billed retention, net billed, and cash received amount for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Project Billing.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_5943
reports_dexterity_job_cost_proje_5943
Retention by project report

The

Anchor
reports_dexterity_job_cost_proje_3060
reports_dexterity_job_cost_proje_3060
 Retention by Project report lists the total contract, retention withheld, retention billed, and billable retention amounts for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Retention.
  2. Use the From and To lookup buttons to select the print range. Choose Insert >>.
  3. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_7169
reports_dexterity_job_cost_proje_7169
Employee summary by project report

The Employee Summary by Project report contains all hours, labor amounts, overhead amounts, and totals for each job number assigned to a project. The transaction beginning and ending dates must match the Date To dates from payroll entry.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Employee Summary.
  2. Select a Project Number.
  3. Enter beginning and ending dates.
  4. Choose Print.

Costs by period by project report

The Costs by Period by Project report lists the actual costs to date and costs per selected period for jobs within the selected projects.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Costs by Period.
  2. Enter the range of years and periods.
  3. Select the project number print range and choose Insert >>.
  4. Choose Print.

Image Added

Anchor
reports_dexterity_job_cost_proje_7783
reports_dexterity_job_cost_proje_7783
Labor summary by project report

The Labor Summary by Project report contains all hours and totals for each job number assigned to a project. The transactions on the report are based on the general ledger posting date. This report is for open jobs only.

  1. Choose Reports > Job Cost > Sorted Reports > Project Reports > Labor Summary.
  2. Select a Project Number.
  3. Enter beginning and ending dates and choose Print.

Image Added