  • The Total Revenue code transaction price amounts for a job cannot exceed the job's Expected Contract amount.
  • To track costs only, you can create a $0.00 revenue code. An example would be warranty costs. The costs from the cost codes assigned to that revenue code will be included in the revenue GL entry after the revenue code has been marked 100% complete.
  • A job cannot be closed if there are cost codes on the job that have yet to be assigned to a revenue code.
  • For revenue to be recognized on a Performance Obligation Contract, the Original Transaction Price on the Job Revenue Codes window must be populated the same month.

Creating a

...

revenue code

  1. On the Job Maintenance window, choose Revenue Code

    Note

    The Revenue Code button is disabled if you chose POC Revenue Recognition in Posting Options window.


  2. Complete the following fields, as needed:
    • Job
      Displays the job information.
    • Included on CO
      Mark to include the Revenue Code on the change order.
    • Revenue Code
      Enter the Revenue Code. This field has a string length of 26. You can also add a note to this revenue code.
    • Description
      Enter a description for the Revenue Code.
    • Revenue Type
      Choose the Revenue Type.
      • Point in Time
        Revenue can only be recognized once (100% complete).
      • Over Time
        Revenue can be recognized incrementally over a period of time.
    • Scheduled Start/Completion Date
      Enter or choose the Scheduled Start and Completion Dates.
    • Actual Start/Completion Date
      Enter the Actual Start and Completion dates.
    • Original Transaction Price
      Enter the original transaction price. 

      Note

      For revenue to be recognized on a Performance Obligation Contract, the Original Transaction Price on the Job Revenue Codes window must be populated the same month.


      • Fixed Amount jobs
        The Original Transaction Price is entered when the Revenue Code is created. Once saved, the amount cannot be edited unless you enter the password used to edit a job's contract amount. A Fixed Amount job can have multiple Revenue Codes assigned.
      • Cost Plus jobs
        This field is not editable. The Original Transaction Price amount increases as costs and/or units are posted to the cost codes assigned to the Revenue Code based on the Profit Types and Profit Amounts on the cost codes. A Cost Plus job can only have one Revenue Code assigned. The cost codes on the job are auto-assigned to the one Revenue Code.
      • Cost Plus NTE jobs
        This field is not editable. The Original Transaction Price amount increases as costs and/or units are posted to the cost codes assigned to the Revenue Code based on the Profit Types and Profit Amounts on the cost codes. The Expected Contract amounts do not exceed the NTE amount. A Cost Plus NTE job can only have one Revenue Code assigned. The cost codes on the job are auto-assigned to the one Revenue Code.
    • Change Order Transaction Price
      This amount displays from the Change Order.
    • Expected Transaction Price
      Displays the total of the Original Transaction Price + Change Order Transaction Price. 

      Note