  • The master subcontractor record is the parent record of the cost code and jobs.
  • When you first create a master subcontractor, some information is copied to the Subcontractors Maintenance window and sub windows. See Create the master subcontractorsMaster Subcontractors..

Using master subcontractors involves the following:

Table of Contents

Anchor
setting_up_and_creating_master_subcontractors
setting_up_and_creating_master_subcontractors
Setting up and

...

Creating Master Subcontractors

Step 1: 
Anchor
job_cost_using_master_subcontrac_523
job_cost_using_master_subcontrac_523
Set up the

...

Master Subcontractor Feature

To use master subcontractors, you must mark the Use Master Subcontractors checkbox in the Subcontractor Options window.

  1. Select Microsoft Dynamics GP > Tools > Setup > Job Cost > Subcontractor Setup > Subcontractor Options.
  2. Mark the Use Master Subcontractors checkbox.
  3. Mark the Track Insurance Dates in Detail (Many per Job) checkbox to enable the Insurance Dates button in the Subcontractor Status and Master Subcontractor Maintenance windows and the ellipsis button in the Insurance Certificate field in the Subcontractors Dates window. You can enter insurance company information for each master subcontractor, including policy numbers and effective dates. Insurance fields are user-definable. See Set up master documents. See Entering insurance dates for a master subcontractor for information on tracking insurance information.
  4. Select Save.

Step 2: 
Anchor
job_cost_using_master_subcontrac_5462
job_cost_using_master_subcontrac_5462
Create the

...

Master Subcontractors

Subcontractors who work on several jobs can be set up as master subcontractors. Master subcontractors allow you to define your vendor-job relationship at the vendor level instead of at the job level.

...

  • Assign a job to a master subcontractor.
  • Assign a cost code to a master subcontractor.
  • Enter insurance dates for a master subcontractor.
  • Create a purchase order for a master subcontractor.
  • Specify required documents for a master subcontractor.
  • Manage lien waivers for a master subcontractor.

Anchor
job_cost_using_master_subcontrac_7625
job_cost_using_master_subcontrac_7625
Assigning a

...

Job to a

...

Master Subcontractor

You can assign jobs to a master subcontractor using the Add Jobs button in the Master Subcontractors Maintenance window.

...

To view a list of jobs assigned to a master subcontractor, select the Stop-and-Go Light indicator in the Master Subcontractors Maintenance window.

Anchor
job_cost_using_master_subcontrac_5393
job_cost_using_master_subcontrac_5393
Assigning a

...

Cost Code to a

...

Master Subcontractor

You can assign cost codes directly to a master subcontractor. Once a job is assigned to a master subcontractor, the cost codes are automatically copied to the subcontractor record assigned to that job.

...

When you assign a cost code to a master subcontractor, you can view that job/subcontractor/cost code association in the Subcontractor Cost Codes window.

Anchor
enter_insurance_dates_subcontractors
enter_insurance_dates_subcontractors
Entering

...

Insurance Dates for a

...

Master Subcontractor

You can enter insurance company information for each master subcontractor, including policy numbers and effective dates. If a policy expires, the vendor and all jobs the vendor is assigned to are put on hold.

  1. Select Cards > Job Cost > Master Subcontractor.
  2. Select a subcontractor, then select Insurance Dates.
  3. Complete the following fields:
    • Required
      Mark the insurance policies that are required for this master subcontractor.
    • Starting, Ending, Received
      Enter the Starting, Ending, and Received dates. The ending date will be copied to the Required Date column in the Subcontractor Dates window for this subcontractor. The required date in the Subcontractor Dates window is automatically set to be the earliest ending date of the required insurance types in the Insurance Dates window. This date is copied to all jobs to which the subcontractor is assigned. If you do not enter an ending date for an insurance type that is marked as required, the subcontractor will be on hold.
    • Required, Available
      Enter coverage amounts. These fields are informational only.
    • Company, Policy Number
      For each insurance company, enter the company name and policy number.
  4. Select Save.

Anchor
job_cost_using_master_subcontrac_1337
job_cost_using_master_subcontrac_1337
Creating a

...

Purchase Order for a

...

Master Subcontractor

  1. You can create a purchase order for a master subcontractor from the Master Subcontractors Maintenance window.
  2. Select Cards > Job Cost > Master Subcontractor.
  3. Select a Subcontractor, then select Create PO.
  4. Complete the Purchase Order Entry window. See the Microsoft Dynamics GP Purchase Order Processing Manual for more information. The Vendor ID fills automatically from the Master Subcontractors Maintenance window.
  5. When entering a purchase order for a master subcontractor, if you select a job to which the master subcontractor is not assigned, a message displays telling you that the selected vendor is not a subcontractor for the selected job. This allows you to assign that subcontractor to that job. Select Yes to add the master subcontractor to the job, or No to not add. If you select Yes, the Subcontractors Maintenance window opens. Complete the window.
Note

If retention needs to be withheld, make sure you enter a contract amount in the Original Contract Amt field in the Subcontractors Maintenance window. Otherwise, retention will not be withheld from Purchase Order Processing or Payables Management.

Automatically

...

Adding Cost Codes to a

...

Subcontractor on a

...

Purchase Order

To automatically add cost codes to a subcontractor when entering a purchase order, mark the Automatically Add Purchase Order Cost Code to Subcontractor checkbox in the Subcontractor Options window. This applies to cost codes assigned to a job that are not linked to a subcontractor in the Subcontractors Maintenance window.

You can automatically add cost codes from the Purchase Order Entry window and Item Detail Entry window.

Specifying

...

Required Documents for a

...

Master Subcontractor

You can specify if a document pertaining to this master subcontractor is required.

...