Use the Job Revenue Code Revision Entry window to revise the percent complete for the selected revenue code. This window displays all previously-posted revenue code revision entries for the job.

To revise a revenue performance objective:

  1. Go to Inquiry > Job Status > Revenue Code Status button > Job Revenue Code Status > Add Revision.
  2. In the Job Revenue Revision Entry window, complete the following fields:
    • Date
      Enter the posting date.
    • Revenue Code
      Choose the revenue code the revision is being made for.
    • Percentage Revision
      Enter the new percentage. The last posted revision for the revision code becomes the current percentage complete. 

      Note

...

    • For Point in Time revenue codes, revenue is not recognized until it is entered as 100% complete. At that point it will be included in the month's revenue entry. If 100% is posted in error, you can enter another lower percentage revision so the revenue code is not included in the month's revenue entry.


    • Description
      Enter a reason for the revision.
  1. Choose Post.