Note

If the Job Status is set to one of the following options for the Job Profit and Loss report, jobs that were closed prior to before the Start/End Period date range are included in the report:

  • All - All Jobs
  • Closed - Closed Jobs
  • All Active - Closed jobs and inactive open jobs.

...

  • Actual % Complete: Actual Cost / Total Forecasted Cost
  • Expected Contract: For Fixed Amount jobs - based on the last day in the end period (end date) of the report. For Cost Plus jobs: Based on the range from the start date of the report to the end date of the report. 

    NoteIf

     If you are viewing a Cost Plus job that began

    prior to

    before the report start date, the Contract Earned amount is adjusted to reflect what was earned in the report range, rather than over the life of the job. For Cost Plus NTE jobs, the Contract Earned displays as zero if the NTE amount is exceeded

    prior to

    before the report start date.

  • Contract Earned: Actual % Complete x Expected Contract
  • Profit Amount: Contract Earned - Actual Cost
  • Markup Percent: (Expected Contract - Total Forecasted Cost) / Total Forecasted Cost
  • Margin Percent: (Expected Contract - Total Forecasted Cost) / Expected Contract

...