The Quantity Variance report compares the estimated unit to date for each cost element with the actual units to date used. The report shows an estimated project variance for each cost code. Total projected variance amounts calculate automatically for all cost elements.

  1. Choose Reports > Job Cost > Job Reports > Variance Reports > Quantity Variance.
  2. Use the lookup buttons in the From and To fields to select the print range. Choose Insert >>.
  3. Choose Print.